Hai Phong official inspects Lao Cai–Hanoi–Hai Phong railway project in western city


On the afternoon of July 8, Standing Vice Chairman of the Hai Phong City People’s Committee Le Anh Quan conducted a field inspection of the Lao Cai–Hanoi–Hai Phong railway construction investment project, in the section passing through the western area of Hai Phong.

The Lao Cai–Hanoi–Hai Phong railway construction investment project through Hai Phong is approximately 89.88 km long and passes through 24 communes, wards and special zones: Cam Giang, Ke Sat, Mao Dien, Binh Giang, Yet Kieu, Gia Loc, Gia Phuc, Tan Ky, Tu Ky, Dai Son, Chi Minh, Ha Dong, An Quang, Quyet Thang, An Khanh, An Hung, Kien Thuy, Kien Minh, Duong Kinh Ward, Hai An Ward, Dong Hai Ward, Nam Do Son Ward, Kien Hai Commune and Cat Hai Special Zone.

The project requires the recovery of approximately 624.13 hectares of land and affects around 6,096 households; the estimated total funding for site clearance is approximately VND 9,753 billion.

To date, the project has determined the number of households requiring resettlement; completed surveying, survey extracts, cadastral extracts and identification of land users to prepare dossiers for recovering land along the main route through the 24 communes, wards and special zones. It has also reviewed and inventoried affected transport and agricultural infrastructure and power-supply systems to support project implementation.

Standing Vice Chairman of the Hai Phong City People’s Committee Le Anh Quan asked localities to accelerate planning for resettlement areas.

After hearing reports from representatives of the relevant departments, agencies and localities, Standing Vice Chairman Le Anh Quan emphasized that the Lao Cai–Hanoi–Hai Phong railway construction investment project is a nationally important project with strategic significance for interregional transport connectivity and for driving socioeconomic development in the northern region in general and Hai Phong in particular. To ensure progress in line with the Prime Minister’s direction, he asked the relevant localities to accelerate planning and construction of resettlement areas; strengthen land management and construction-order management; and fully and seriously carry out survey extracts, cadastral extracts, verification of land origins and determination of resettlement-support eligibility for residents.

The Standing Vice Chairman also assigned the relevant departments and agencies to closely coordinate with localities on compensation and site clearance, ensuring consistency, compliance with the schedule and conformity with the law.

Inspecting the handling of administrative procedures at the Yet Kieu Commune Public Administration Service Center.
Inspecting the handling of administrative procedures at the Gia Phuc Commune Public Administration Service Center.

Also on the afternoon of July 8, Standing Vice Chairman Le Anh Quan inspected the handling of administrative procedures at the Public Administration Service Centers of Yet Kieu Commune and Gia Phuc Commune.

Recognizing the localities’ efforts during the first days of implementing the two-tier local government model, the Standing Vice Chairman praised the sense of responsibility and initiative of grassroots officials and civil servants. He also asked the localities to continue reviewing and improving their facilities and technical infrastructure and to raise service quality so as to better meet the needs of residents and businesses./.

Source: Hai Phong City E-Portal